June 2023

With work on the road and utilities now complete, the Aspen Homes team have turned their attention to the renovation of Tretower House. The house has been taken back to the studs to allow us to properly inspect the state of the property. New steel, concrete and timber lintels have begun to be installed to[…]

Read More

With the surface water drainage system and road base now in place, we have had contractors on site to install kerbs and pour tarmac on the road base. This can now be used as our temporary construction road for deliveries and vehicular access throughout the project. Once construction is finished at Willow Place, the road[…]

Read More